CAMP
1 Introduction to Project Management
1.1 Overview of Project Management
1.2 Project Life Cycle
1.3 Project Management Processes
1.4 Project Management Knowledge Areas
1.5 Project Management Frameworks
2 Project Environment
2.1 Organizational Structures
2.2 Organizational Process Assets
2.3 Enterprise Environmental Factors
2.4 Project Governance
2.5 Project Stakeholders
3 Project Management Processes
3.1 Initiating Process Group
3.2 Planning Process Group
3.3 Executing Process Group
3.4 Monitoring and Controlling Process Group
3.5 Closing Process Group
4 Integration Management
4.1 Develop Project Charter
4.2 Develop Project Management Plan
4.3 Direct and Manage Project Work
4.4 Monitor and Control Project Work
4.5 Perform Integrated Change Control
4.6 Close Project or Phase
5 Scope Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create Work Breakdown Structure (WBS)
5.5 Validate Scope
5.6 Control Scope
6 Time Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7 Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8 Quality Management
8.1 Plan Quality Management
8.2 Perform Quality Assurance
8.3 Control Quality
9 Human Resource Management
9.1 Develop Human Resource Plan
9.2 Acquire Project Team
9.3 Develop Project Team
9.4 Manage Project Team
10 Communications Management
10.1 Plan Communications Management
10.2 Manage Communications
10.3 Control Communications
11 Risk Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
11.6 Control Risks
12 Procurement Management
12.1 Plan Procurement Management
12.2 Conduct Procurements
12.3 Control Procurements
12.4 Close Procurements
13 Stakeholder Management
13.1 Identify Stakeholders
13.2 Plan Stakeholder Management
13.3 Manage Stakeholder Engagement
13.4 Control Stakeholder Engagement
14 Professional and Social Responsibility
14.1 Ethical Considerations
14.2 Social Responsibility
14.3 Professional Conduct
15 Exam Preparation
15.1 Exam Format and Structure
15.2 Study Tips and Strategies
15.3 Practice Questions and Mock Exams
15.4 Time Management During the Exam
15.5 Post-Exam Review and Continuous Learning
Perform Integrated Change Control Explained

Perform Integrated Change Control Explained

Perform Integrated Change Control is a critical process in project management that involves identifying, evaluating, and managing changes to the project's scope, schedule, cost, and other components. This process ensures that all changes are properly documented, approved, and implemented, maintaining the project's integrity and alignment with its objectives.

Key Concepts

1. Change Identification

Change Identification involves recognizing and documenting any requests for changes to the project. These changes can originate from various sources, including stakeholders, project team members, or external factors. Identifying changes early is crucial for effective change management.

Example: In a software development project, a change request might come from a client who wants to add a new feature to the application. The project manager documents this request and initiates the change control process.

2. Change Evaluation

Change Evaluation involves assessing the impact of the proposed changes on the project's scope, schedule, cost, and quality. This evaluation helps in determining whether the changes are feasible and whether they should be approved or rejected.

Example: For the new feature request in the software project, the project manager evaluates the impact on the timeline, budget, and resource allocation. If the change is feasible and aligns with the project's objectives, it is considered for approval.

3. Change Approval

Change Approval involves obtaining formal authorization for the proposed changes. This process typically involves a change control board (CCB) or similar authority that reviews the change request and decides whether to approve, reject, or defer the change.

Example: The software project's CCB reviews the evaluation report and decides to approve the new feature request. The project manager then updates the project management plan and communicates the approved change to the team.

4. Change Implementation

Change Implementation involves integrating the approved changes into the project management plan and executing them. This process ensures that the changes are properly documented and that the project team is aware of the new requirements.

Example: After the new feature is approved, the project manager updates the project schedule, budget, and scope documents. The development team then implements the new feature according to the updated plan.

5. Change Documentation

Change Documentation involves recording all changes and their impacts on the project. This documentation helps in maintaining a historical record of changes, which can be useful for future projects and audits.

Example: The project manager maintains a change log that records all change requests, their evaluations, approvals, and implementations. This log is reviewed periodically to ensure that all changes are properly documented and tracked.

6. Change Communication

Change Communication involves informing all stakeholders about the approved changes and their impacts. Effective communication ensures that everyone is aware of the changes and can adjust their activities accordingly.

Example: The project manager sends out a communication plan update to all stakeholders, detailing the new feature and its impact on the project timeline and budget. This ensures that everyone is aligned and prepared for the changes.