Project Management Professional (PMP) for engineering project management roles
1 Introduction to Project Management
1-1 Definition of Project Management
1-2 Project Management Framework
1-3 Project Management Knowledge Areas
1-4 Project Management Processes
1-5 Project Life Cycle
2 Project Integration Management
2-1 Develop Project Charter
2-2 Develop Project Management Plan
2-3 Direct and Manage Project Work
2-4 Monitor and Control Project Work
2-5 Perform Integrated Change Control
2-6 Close Project or Phase
3 Project Scope Management
3-1 Plan Scope Management
3-2 Collect Requirements
3-3 Define Scope
3-4 Create WBS
3-5 Validate Scope
3-6 Control Scope
4 Project Time Management
4-1 Plan Schedule Management
4-2 Define Activities
4-3 Sequence Activities
4-4 Estimate Activity Durations
4-5 Develop Schedule
4-6 Control Schedule
5 Project Cost Management
5-1 Plan Cost Management
5-2 Estimate Costs
5-3 Determine Budget
5-4 Control Costs
6 Project Quality Management
6-1 Plan Quality Management
6-2 Perform Quality Assurance
6-3 Control Quality
7 Project Human Resource Management
7-1 Develop Human Resource Plan
7-2 Acquire Project Team
7-3 Develop Project Team
7-4 Manage Project Team
8 Project Communications Management
8-1 Plan Communications Management
8-2 Manage Communications
8-3 Control Communications
9 Project Risk Management
9-1 Plan Risk Management
9-2 Identify Risks
9-3 Perform Qualitative Risk Analysis
9-4 Perform Quantitative Risk Analysis
9-5 Plan Risk Responses
9-6 Control Risks
10 Project Procurement Management
10-1 Plan Procurement Management
10-2 Conduct Procurements
10-3 Control Procurements
10-4 Close Procurements
11 Project Stakeholder Management
11-1 Identify Stakeholders
11-2 Plan Stakeholder Management
11-3 Manage Stakeholder Engagement
11-4 Control Stakeholder Engagement
12 Engineering Project Management Specialization
12-1 Engineering Project Life Cycle
12-2 Engineering Project Planning and Scheduling
12-3 Engineering Project Cost Estimation
12-4 Engineering Project Risk Management
12-5 Engineering Project Quality Management
12-6 Engineering Project Procurement Management
12-7 Engineering Project Stakeholder Management
12-8 Engineering Project Communication Management
12-9 Engineering Project Integration Management
12-10 Engineering Project Human Resource Management
13 Tools and Techniques for Engineering Project Management
13-1 Project Management Software
13-2 Scheduling Tools
13-3 Cost Estimation Tools
13-4 Risk Management Tools
13-5 Quality Management Tools
13-6 Communication Tools
13-7 Stakeholder Management Tools
13-8 Procurement Management Tools
14 Case Studies and Practical Applications
14-1 Case Study Analysis
14-2 Practical Application of Project Management in Engineering Projects
14-3 Lessons Learned from Engineering Projects
15 Certification Preparation
15-1 Overview of PMP Certification Exam
15-2 Exam Format and Structure
15-3 Study Tips and Strategies
15-4 Practice Questions and Mock Exams
15-5 Certification Application Process
12.2 Engineering Project Planning and Scheduling

12.2 Engineering Project Planning and Scheduling - 12.2 Engineering Project Planning and Scheduling

Engineering Project Planning and Scheduling is a critical process in project management that involves defining the project scope, identifying tasks, estimating resources, and creating a timeline to ensure the project is completed on time and within budget. Effective planning and scheduling are essential for managing complex engineering projects.

Key Concepts

1. Work Breakdown Structure (WBS)

The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to accomplish project objectives and create deliverables. It breaks down the project into smaller, more manageable components, making it easier to plan, schedule, and control.

Example: In an engineering project to design a new product, the WBS might include phases such as concept development, detailed design, prototyping, testing, and production. Each phase can be further broken down into specific tasks.

2. Activity Definition

Activity Definition involves identifying the specific activities required to produce the project deliverables. These activities are the individual tasks that need to be completed to achieve the project objectives. Defining activities helps in estimating time, cost, and resources.

Example: For a construction project, activity definition might include tasks such as site preparation, foundation laying, framing, roofing, and finishing. Each task is a specific activity that contributes to the overall project completion.

3. Activity Sequencing

Activity Sequencing involves determining the dependencies and order of activities. This includes identifying which activities must be completed before others can start (precedence relationships). Sequencing helps in creating a logical flow of work and identifying critical paths.

Example: In an engineering project, activity sequencing might show that the detailed design must be completed before prototyping can begin, and prototyping must be finished before testing can start.

4. Activity Duration Estimation

Activity Duration Estimation involves determining the time required to complete each activity. This estimation is based on historical data, expert judgment, and other relevant factors. Accurate duration estimation is crucial for creating realistic project schedules.

Example: For a software development project, activity duration estimation might involve estimating the time required for coding, testing, and documentation. Historical data from similar projects can be used to make these estimates.

5. Schedule Development

Schedule Development involves creating a timeline that outlines the start and end dates for each activity. This includes incorporating dependencies, resource availability, and constraints. The schedule helps in visualizing the project timeline and identifying potential delays.

Example: In an engineering project, schedule development might involve creating a Gantt chart that shows the start and end dates for each phase and activity. This chart helps in tracking progress and managing timelines.

6. Critical Path Method (CPM)

The Critical Path Method (CPM) is a project management technique used to determine the sequence of activities that directly affect the project duration. The critical path is the longest path through the project schedule, and any delay in these activities will delay the entire project.

Example: For a construction project, the critical path might include activities such as foundation laying, framing, and roofing. Any delay in these activities will directly impact the project completion date.

7. Resource Leveling

Resource Leveling involves adjusting the project schedule to optimize the allocation of resources. This includes resolving resource conflicts, such as over-allocation or under-allocation, to ensure that resources are used efficiently and effectively.

Example: In an engineering project, resource leveling might involve adjusting the schedule to ensure that key engineers are not working on multiple tasks simultaneously, which could lead to delays and inefficiencies.

8. Schedule Compression

Schedule Compression involves reducing the project duration without reducing the project scope. Techniques such as crashing (adding more resources) and fast tracking (performing activities in parallel) are used to compress the schedule and meet tight deadlines.

Example: For a software development project, schedule compression might involve adding more developers to critical tasks or fast-tracking the testing phase by starting it earlier than originally planned.

Examples and Analogies

Think of engineering project planning and scheduling as building a house. Just as you need to break down the construction process into smaller tasks (WBS), define the order of these tasks (activity sequencing), estimate the time required for each task (duration estimation), and create a timeline (schedule development), you need to plan and schedule your engineering project to ensure it is completed on time and within budget.

For instance, in an engineering project to design and build a new product, effective planning and scheduling would involve creating a detailed WBS, defining the activities required for each phase, sequencing these activities based on dependencies, estimating the duration of each activity, and developing a schedule that outlines the project timeline. By using techniques such as CPM, resource leveling, and schedule compression, the project team can ensure that the project stays on track and meets its objectives.