Project Management Professional (PMP) for engineering project management roles
1 Introduction to Project Management
1-1 Definition of Project Management
1-2 Project Management Framework
1-3 Project Management Knowledge Areas
1-4 Project Management Processes
1-5 Project Life Cycle
2 Project Integration Management
2-1 Develop Project Charter
2-2 Develop Project Management Plan
2-3 Direct and Manage Project Work
2-4 Monitor and Control Project Work
2-5 Perform Integrated Change Control
2-6 Close Project or Phase
3 Project Scope Management
3-1 Plan Scope Management
3-2 Collect Requirements
3-3 Define Scope
3-4 Create WBS
3-5 Validate Scope
3-6 Control Scope
4 Project Time Management
4-1 Plan Schedule Management
4-2 Define Activities
4-3 Sequence Activities
4-4 Estimate Activity Durations
4-5 Develop Schedule
4-6 Control Schedule
5 Project Cost Management
5-1 Plan Cost Management
5-2 Estimate Costs
5-3 Determine Budget
5-4 Control Costs
6 Project Quality Management
6-1 Plan Quality Management
6-2 Perform Quality Assurance
6-3 Control Quality
7 Project Human Resource Management
7-1 Develop Human Resource Plan
7-2 Acquire Project Team
7-3 Develop Project Team
7-4 Manage Project Team
8 Project Communications Management
8-1 Plan Communications Management
8-2 Manage Communications
8-3 Control Communications
9 Project Risk Management
9-1 Plan Risk Management
9-2 Identify Risks
9-3 Perform Qualitative Risk Analysis
9-4 Perform Quantitative Risk Analysis
9-5 Plan Risk Responses
9-6 Control Risks
10 Project Procurement Management
10-1 Plan Procurement Management
10-2 Conduct Procurements
10-3 Control Procurements
10-4 Close Procurements
11 Project Stakeholder Management
11-1 Identify Stakeholders
11-2 Plan Stakeholder Management
11-3 Manage Stakeholder Engagement
11-4 Control Stakeholder Engagement
12 Engineering Project Management Specialization
12-1 Engineering Project Life Cycle
12-2 Engineering Project Planning and Scheduling
12-3 Engineering Project Cost Estimation
12-4 Engineering Project Risk Management
12-5 Engineering Project Quality Management
12-6 Engineering Project Procurement Management
12-7 Engineering Project Stakeholder Management
12-8 Engineering Project Communication Management
12-9 Engineering Project Integration Management
12-10 Engineering Project Human Resource Management
13 Tools and Techniques for Engineering Project Management
13-1 Project Management Software
13-2 Scheduling Tools
13-3 Cost Estimation Tools
13-4 Risk Management Tools
13-5 Quality Management Tools
13-6 Communication Tools
13-7 Stakeholder Management Tools
13-8 Procurement Management Tools
14 Case Studies and Practical Applications
14-1 Case Study Analysis
14-2 Practical Application of Project Management in Engineering Projects
14-3 Lessons Learned from Engineering Projects
15 Certification Preparation
15-1 Overview of PMP Certification Exam
15-2 Exam Format and Structure
15-3 Study Tips and Strategies
15-4 Practice Questions and Mock Exams
15-5 Certification Application Process
4.4 Estimate Activity Durations

4.4 Estimate Activity Durations - 4.4 Estimate Activity Durations

Estimate Activity Durations is a critical process in Project Time Management that involves determining the number of work periods needed to complete individual activities with the estimated resources. Accurate duration estimates are essential for creating a realistic project schedule and ensuring that the project stays on track.

Key Concepts

1. Work Breakdown Structure (WBS)

The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team. It breaks down the project scope into manageable components, making it easier to estimate the duration of each activity. The WBS is a key input for estimating activity durations.

Example: For a construction project, the WBS might start with the overall project (Level 1), then break it down into major components like foundations, superstructure, and finishing (Level 2), and further into specific tasks like pouring concrete, installing girders, and painting (Level 3).

2. Activity List

The Activity List is a comprehensive list of all activities required to complete the project. Each activity in the list should be clearly defined and include a description of the work to be performed. The Activity List is used to identify the specific activities for which duration estimates are needed.

Example: In a software development project, the Activity List might include tasks such as "Design User Interface," "Develop Back-End Logic," "Perform Unit Testing," and "Conduct User Training."

3. Resource Estimates

Resource Estimates involve determining the types and quantities of resources required to complete each activity. Resources can include personnel, equipment, materials, and facilities. Accurate resource estimates are crucial for estimating activity durations, as the availability and efficiency of resources directly impact the time required to complete tasks.

Example: For a manufacturing project, resource estimates might include the number of machines, the availability of skilled labor, and the quantities of raw materials needed for each production phase.

4. Duration Estimating Techniques

Duration Estimating Techniques are methods used to calculate the time required to complete activities. These techniques include Analogous Estimating, Parametric Estimating, Three-Point Estimating, and Expert Judgment. The choice of technique depends on the availability of historical data, the complexity of the project, and the accuracy required.

Example: Analogous Estimating might be used for a new construction project by comparing it to a similar past project to estimate the duration of activities. Parametric Estimating could be used in a software development project by using historical data to calculate the time required per line of code.

5. Three-Point Estimating

Three-Point Estimating involves calculating an average duration based on three estimates: the most likely duration (M), the optimistic duration (O), and the pessimistic duration (P). This technique helps account for uncertainty and variability in the duration estimates. The formula used is often the Beta Distribution: (O + 4M + P) / 6.

Example: For an activity in a construction project, the optimistic duration might be 5 days, the most likely duration 7 days, and the pessimistic duration 10 days. The estimated duration would be (5 + 4*7 + 10) / 6 = 7.33 days.

Conclusion

Estimate Activity Durations is a foundational process that sets the stage for effective project scheduling. By creating detailed duration estimates for each activity, project managers can ensure that the project schedule is realistic and achievable. Accurate duration estimates are essential for managing project timelines, allocating resources, and achieving project success.