Project Management Professional (PMP) for engineering project management roles
1 Introduction to Project Management
1-1 Definition of Project Management
1-2 Project Management Framework
1-3 Project Management Knowledge Areas
1-4 Project Management Processes
1-5 Project Life Cycle
2 Project Integration Management
2-1 Develop Project Charter
2-2 Develop Project Management Plan
2-3 Direct and Manage Project Work
2-4 Monitor and Control Project Work
2-5 Perform Integrated Change Control
2-6 Close Project or Phase
3 Project Scope Management
3-1 Plan Scope Management
3-2 Collect Requirements
3-3 Define Scope
3-4 Create WBS
3-5 Validate Scope
3-6 Control Scope
4 Project Time Management
4-1 Plan Schedule Management
4-2 Define Activities
4-3 Sequence Activities
4-4 Estimate Activity Durations
4-5 Develop Schedule
4-6 Control Schedule
5 Project Cost Management
5-1 Plan Cost Management
5-2 Estimate Costs
5-3 Determine Budget
5-4 Control Costs
6 Project Quality Management
6-1 Plan Quality Management
6-2 Perform Quality Assurance
6-3 Control Quality
7 Project Human Resource Management
7-1 Develop Human Resource Plan
7-2 Acquire Project Team
7-3 Develop Project Team
7-4 Manage Project Team
8 Project Communications Management
8-1 Plan Communications Management
8-2 Manage Communications
8-3 Control Communications
9 Project Risk Management
9-1 Plan Risk Management
9-2 Identify Risks
9-3 Perform Qualitative Risk Analysis
9-4 Perform Quantitative Risk Analysis
9-5 Plan Risk Responses
9-6 Control Risks
10 Project Procurement Management
10-1 Plan Procurement Management
10-2 Conduct Procurements
10-3 Control Procurements
10-4 Close Procurements
11 Project Stakeholder Management
11-1 Identify Stakeholders
11-2 Plan Stakeholder Management
11-3 Manage Stakeholder Engagement
11-4 Control Stakeholder Engagement
12 Engineering Project Management Specialization
12-1 Engineering Project Life Cycle
12-2 Engineering Project Planning and Scheduling
12-3 Engineering Project Cost Estimation
12-4 Engineering Project Risk Management
12-5 Engineering Project Quality Management
12-6 Engineering Project Procurement Management
12-7 Engineering Project Stakeholder Management
12-8 Engineering Project Communication Management
12-9 Engineering Project Integration Management
12-10 Engineering Project Human Resource Management
13 Tools and Techniques for Engineering Project Management
13-1 Project Management Software
13-2 Scheduling Tools
13-3 Cost Estimation Tools
13-4 Risk Management Tools
13-5 Quality Management Tools
13-6 Communication Tools
13-7 Stakeholder Management Tools
13-8 Procurement Management Tools
14 Case Studies and Practical Applications
14-1 Case Study Analysis
14-2 Practical Application of Project Management in Engineering Projects
14-3 Lessons Learned from Engineering Projects
15 Certification Preparation
15-1 Overview of PMP Certification Exam
15-2 Exam Format and Structure
15-3 Study Tips and Strategies
15-4 Practice Questions and Mock Exams
15-5 Certification Application Process
4 Project Time Management

4 Project Time Management - 4 Project Time Management

Project Time Management is a critical aspect of project management that ensures the project is completed within the defined schedule. It involves a series of processes that help plan, estimate, schedule, and control the project timeline to meet the project's objectives.

Key Concepts

1. Activity Definition

Activity Definition involves identifying and documenting the specific actions required to produce the project deliverables. This process breaks down the project work into smaller, more manageable tasks. The output of this process is a list of activities that will be used to develop the project schedule.

Example: In a construction project, activity definition might include tasks such as site preparation, foundation laying, framing, and roofing. Each of these tasks is a discrete activity that contributes to the overall project completion.

2. Activity Sequencing

Activity Sequencing involves identifying and documenting the relationships between project activities. This process determines the order in which activities need to be performed to ensure the project progresses smoothly. Dependency relationships, such as finish-to-start, start-to-start, finish-to-finish, and start-to-finish, are established during this process.

Example: For a software development project, activity sequencing might dictate that coding cannot begin until the design phase is complete. Similarly, testing activities must follow the coding phase. These dependencies are mapped out to create a logical flow of work.

3. Activity Duration Estimating

Activity Duration Estimating involves estimating the number of work periods required to complete individual activities. This process uses historical data, expert judgment, and other estimating techniques to determine the time required for each activity. Accurate duration estimates are crucial for developing a realistic project schedule.

Example: In an engineering project, the duration of an activity like "Design Review" might be estimated based on past projects and the complexity of the current design. If similar reviews took 5 days in the past, the estimate for the current project might be adjusted based on the current scope and team capacity.

4. Schedule Development

Schedule Development involves integrating the project activities, dependencies, and duration estimates to create a comprehensive project schedule. This process uses scheduling tools and techniques, such as Gantt charts, critical path method (CPM), and program evaluation and review technique (PERT), to visualize and manage the project timeline.

Example: For a manufacturing project, the schedule development might involve creating a Gantt chart that shows the start and end dates of each manufacturing activity, along with their dependencies. The critical path, which represents the longest path of dependent activities, would be highlighted to identify the key milestones and potential bottlenecks.

5. Schedule Control

Schedule Control involves monitoring the project schedule to ensure it stays on track and making adjustments as necessary. This process includes tracking progress against the schedule, identifying variances, and implementing corrective actions. Effective schedule control ensures that the project meets its deadlines and objectives.

Example: In a project to build a new facility, schedule control might involve weekly progress meetings to review the current status against the Gantt chart. If a delay is identified in the "Site Preparation" activity, the project manager might reallocate resources or adjust the schedule to mitigate the impact on the overall project timeline.