Project Management Professional (PMP) for engineering project management roles
1 Introduction to Project Management
1-1 Definition of Project Management
1-2 Project Management Framework
1-3 Project Management Knowledge Areas
1-4 Project Management Processes
1-5 Project Life Cycle
2 Project Integration Management
2-1 Develop Project Charter
2-2 Develop Project Management Plan
2-3 Direct and Manage Project Work
2-4 Monitor and Control Project Work
2-5 Perform Integrated Change Control
2-6 Close Project or Phase
3 Project Scope Management
3-1 Plan Scope Management
3-2 Collect Requirements
3-3 Define Scope
3-4 Create WBS
3-5 Validate Scope
3-6 Control Scope
4 Project Time Management
4-1 Plan Schedule Management
4-2 Define Activities
4-3 Sequence Activities
4-4 Estimate Activity Durations
4-5 Develop Schedule
4-6 Control Schedule
5 Project Cost Management
5-1 Plan Cost Management
5-2 Estimate Costs
5-3 Determine Budget
5-4 Control Costs
6 Project Quality Management
6-1 Plan Quality Management
6-2 Perform Quality Assurance
6-3 Control Quality
7 Project Human Resource Management
7-1 Develop Human Resource Plan
7-2 Acquire Project Team
7-3 Develop Project Team
7-4 Manage Project Team
8 Project Communications Management
8-1 Plan Communications Management
8-2 Manage Communications
8-3 Control Communications
9 Project Risk Management
9-1 Plan Risk Management
9-2 Identify Risks
9-3 Perform Qualitative Risk Analysis
9-4 Perform Quantitative Risk Analysis
9-5 Plan Risk Responses
9-6 Control Risks
10 Project Procurement Management
10-1 Plan Procurement Management
10-2 Conduct Procurements
10-3 Control Procurements
10-4 Close Procurements
11 Project Stakeholder Management
11-1 Identify Stakeholders
11-2 Plan Stakeholder Management
11-3 Manage Stakeholder Engagement
11-4 Control Stakeholder Engagement
12 Engineering Project Management Specialization
12-1 Engineering Project Life Cycle
12-2 Engineering Project Planning and Scheduling
12-3 Engineering Project Cost Estimation
12-4 Engineering Project Risk Management
12-5 Engineering Project Quality Management
12-6 Engineering Project Procurement Management
12-7 Engineering Project Stakeholder Management
12-8 Engineering Project Communication Management
12-9 Engineering Project Integration Management
12-10 Engineering Project Human Resource Management
13 Tools and Techniques for Engineering Project Management
13-1 Project Management Software
13-2 Scheduling Tools
13-3 Cost Estimation Tools
13-4 Risk Management Tools
13-5 Quality Management Tools
13-6 Communication Tools
13-7 Stakeholder Management Tools
13-8 Procurement Management Tools
14 Case Studies and Practical Applications
14-1 Case Study Analysis
14-2 Practical Application of Project Management in Engineering Projects
14-3 Lessons Learned from Engineering Projects
15 Certification Preparation
15-1 Overview of PMP Certification Exam
15-2 Exam Format and Structure
15-3 Study Tips and Strategies
15-4 Practice Questions and Mock Exams
15-5 Certification Application Process
4.6 Control Schedule

4.6 Control Schedule - 4.6 Control Schedule

Control Schedule is a critical process in Project Time Management that involves monitoring the status of the project schedule to update the project progress and manage changes to the schedule baseline. This process ensures that the project stays on track and meets its deadlines.

Key Concepts

1. Schedule Baseline

The Schedule Baseline is the approved version of the project schedule, including the start and end dates of project activities. It serves as a reference point for measuring performance and managing changes. Any deviations from the schedule baseline must be carefully monitored and controlled.

Example: In a construction project, the schedule baseline might include the planned start and end dates for each phase, such as site preparation, foundation laying, and building construction. Any delays in these phases would be tracked against this baseline.

2. Schedule Performance Measurement

Schedule Performance Measurement involves tracking the actual progress of the project against the planned schedule. This includes calculating schedule performance indices (SPI) and schedule variance (SV) to assess how well the project is progressing. These metrics help identify whether the project is ahead of, on, or behind schedule.

Example: For a software development project, if the planned schedule indicates that 50% of coding should be completed by a certain date, but only 40% is actually completed, the schedule variance would be negative, indicating a delay.

3. Schedule Forecasting

Schedule Forecasting involves predicting the future performance of the project based on current and historical data. This includes estimating the project's completion date and identifying potential risks that could impact the schedule. Forecasting helps in making informed decisions to keep the project on track.

Example: In an engineering project, if a critical component is delayed, schedule forecasting might predict that the overall project completion date will be pushed back by two weeks. This information can be used to adjust the project plan and allocate additional resources to mitigate the delay.

4. Performance Reviews

Performance Reviews are periodic assessments of the project's progress against the schedule baseline. These reviews involve comparing the actual performance with the planned performance, identifying variances, and analyzing the causes of any deviations. Performance reviews help in taking corrective actions to bring the project back on schedule.

Example: For a manufacturing project, a performance review might reveal that the production rate is lower than expected due to machine breakdowns. The review would identify this as a variance and recommend corrective actions, such as scheduling maintenance or acquiring additional machines.

5. Change Requests

Change Requests are formal proposals to modify any aspect of the project schedule, including the start and end dates of activities, resource allocation, or the sequence of tasks. These requests must be documented, evaluated, and approved through a formal change control process to ensure that changes do not adversely affect the project.

Example: In a project to build a new facility, a change request might be submitted to extend the deadline for the completion of the interior design phase. This request would need to be evaluated for its impact on the overall project timeline and budget before approval.

6. Corrective Actions

Corrective Actions are measures taken to address any variances or deviations from the schedule baseline. These actions aim to bring the project back on track and ensure that it meets its deadlines. Corrective actions can include reallocating resources, adjusting the schedule, or implementing process improvements.

Example: If a construction project is behind schedule due to delays in material delivery, corrective actions might include expediting the delivery process, reallocating workers to different tasks, or adjusting the project timeline to accommodate the delay.