PMP
1 Introduction to Project Management
1.1 Definition of Project Management
1.2 Importance of Project Management
1.3 Project Management Framework
1.4 Project Life Cycle
1.5 Project Management Knowledge Areas
1.6 Project Management Process Groups
2 Project Environment
2.1 Organizational Structures
2.2 Organizational Process Assets
2.3 Enterprise Environmental Factors
2.4 Stakeholder Management
2.5 Project Governance
3 Project Integration Management
3.1 Develop Project Charter
3.2 Develop Project Management Plan
3.3 Direct and Manage Project Work
3.4 Monitor and Control Project Work
3.5 Perform Integrated Change Control
3.6 Close Project or Phase
4 Project Scope Management
4.1 Plan Scope Management
4.2 Collect Requirements
4.3 Define Scope
4.4 Create WBS
4.5 Validate Scope
4.6 Control Scope
5 Project Time Management
5.1 Plan Schedule Management
5.2 Define Activities
5.3 Sequence Activities
5.4 Estimate Activity Durations
5.5 Develop Schedule
5.6 Control Schedule
6 Project Cost Management
6.1 Plan Cost Management
6.2 Estimate Costs
6.3 Determine Budget
6.4 Control Costs
7 Project Quality Management
7.1 Plan Quality Management
7.2 Perform Quality Assurance
7.3 Control Quality
8 Project Resource Management
8.1 Plan Resource Management
8.2 Estimate Activity Resources
8.3 Acquire Resources
8.4 Develop Team
8.5 Manage Team
8.6 Control Resources
9 Project Communications Management
9.1 Plan Communications Management
9.2 Manage Communications
9.3 Monitor Communications
10 Project Risk Management
10.1 Plan Risk Management
10.2 Identify Risks
10.3 Perform Qualitative Risk Analysis
10.4 Perform Quantitative Risk Analysis
10.5 Plan Risk Responses
10.6 Implement Risk Responses
10.7 Monitor Risks
11 Project Procurement Management
11.1 Plan Procurement Management
11.2 Conduct Procurements
11.3 Control Procurements
12 Project Stakeholder Management
12.1 Identify Stakeholders
12.2 Plan Stakeholder Engagement
12.3 Manage Stakeholder Engagement
12.4 Monitor Stakeholder Engagement
13 Professional and Social Responsibility
13.1 Ethical Considerations in Project Management
13.2 Social Responsibility in Project Management
14 Exam Preparation
14.1 Exam Format and Structure
14.2 Study Tips and Strategies
14.3 Practice Questions and Mock Exams
14.4 Time Management During the Exam
14.5 Post-Exam Review and Feedback

5 1 Plan Schedule Management

5.1 Plan Schedule Management Explained

5.1 Plan Schedule Management Explained

Plan Schedule Management is a critical process in project management that involves creating a schedule management plan. This plan outlines how the project schedule will be defined, developed, monitored, controlled, and validated. It ensures that the project team and stakeholders understand the timing and sequencing of project activities, thereby facilitating effective project execution and control.

Key Concepts

1. Schedule Management Plan

The Schedule Management Plan is a subsidiary plan of the project management plan. It provides detailed guidance on how to manage the project schedule throughout its lifecycle. This plan includes procedures for defining the schedule, developing the schedule model, monitoring the schedule, and controlling changes to the schedule.

Example: For a construction project, the schedule management plan might include guidelines for defining the project schedule, such as specifying the start and end dates for each phase of construction. It would also outline how changes to the schedule will be managed, such as requiring approval from a steering committee for any significant delays.

2. Schedule Model

The Schedule Model is a representation of the project schedule that includes the schedule activities, their dependencies, and the sequencing of these activities. It helps in visualizing the project timeline and understanding the critical path, which is the sequence of activities that determines the minimum project duration.

Example: In a software development project, the schedule model might include a Gantt chart that shows the start and end dates for each development phase, such as "Requirements Gathering," "Design," "Development," and "Testing." The critical path in this model would highlight the activities that, if delayed, would push back the entire project timeline.

3. Schedule Baseline

The Schedule Baseline is a component of the project management plan that includes the approved project schedule model and the corresponding schedule network diagrams. It serves as a reference point for measuring schedule performance and managing schedule changes. The schedule baseline is established during the Plan Schedule Management process.

Example: For a marketing campaign, the schedule baseline might include the project schedule model, which outlines the timeline for activities such as "Campaign Planning," "Content Creation," and "Execution." This baseline ensures that all team members have a clear understanding of the project's timeline and can monitor progress against it.

4. Schedule Control

Schedule Control involves managing changes to the project schedule. It ensures that any changes to the schedule are properly evaluated, approved, and implemented. Effective schedule control helps prevent delays and ensures that the project stays on track.

Example: For a construction project, schedule control might involve a change control process where any proposed changes to the project schedule are reviewed by a change control board. The board evaluates the impact of the changes on the project timeline, budget, and quality, and decides whether to approve or reject the changes.

5. Schedule Monitoring

Schedule Monitoring involves tracking the project's progress against the schedule baseline. It helps in identifying any deviations from the planned schedule and taking corrective actions to keep the project on track. Monitoring the schedule ensures that the project stays aligned with its objectives and constraints.

Example: In a software development project, schedule monitoring might involve regular status meetings where the project team reviews the progress of each development phase. If any phase is behind schedule, the team can discuss potential solutions, such as reallocating resources or adjusting the scope, to get back on track.