PMP
1 Introduction to Project Management
1.1 Definition of Project Management
1.2 Importance of Project Management
1.3 Project Management Framework
1.4 Project Life Cycle
1.5 Project Management Knowledge Areas
1.6 Project Management Process Groups
2 Project Environment
2.1 Organizational Structures
2.2 Organizational Process Assets
2.3 Enterprise Environmental Factors
2.4 Stakeholder Management
2.5 Project Governance
3 Project Integration Management
3.1 Develop Project Charter
3.2 Develop Project Management Plan
3.3 Direct and Manage Project Work
3.4 Monitor and Control Project Work
3.5 Perform Integrated Change Control
3.6 Close Project or Phase
4 Project Scope Management
4.1 Plan Scope Management
4.2 Collect Requirements
4.3 Define Scope
4.4 Create WBS
4.5 Validate Scope
4.6 Control Scope
5 Project Time Management
5.1 Plan Schedule Management
5.2 Define Activities
5.3 Sequence Activities
5.4 Estimate Activity Durations
5.5 Develop Schedule
5.6 Control Schedule
6 Project Cost Management
6.1 Plan Cost Management
6.2 Estimate Costs
6.3 Determine Budget
6.4 Control Costs
7 Project Quality Management
7.1 Plan Quality Management
7.2 Perform Quality Assurance
7.3 Control Quality
8 Project Resource Management
8.1 Plan Resource Management
8.2 Estimate Activity Resources
8.3 Acquire Resources
8.4 Develop Team
8.5 Manage Team
8.6 Control Resources
9 Project Communications Management
9.1 Plan Communications Management
9.2 Manage Communications
9.3 Monitor Communications
10 Project Risk Management
10.1 Plan Risk Management
10.2 Identify Risks
10.3 Perform Qualitative Risk Analysis
10.4 Perform Quantitative Risk Analysis
10.5 Plan Risk Responses
10.6 Implement Risk Responses
10.7 Monitor Risks
11 Project Procurement Management
11.1 Plan Procurement Management
11.2 Conduct Procurements
11.3 Control Procurements
12 Project Stakeholder Management
12.1 Identify Stakeholders
12.2 Plan Stakeholder Engagement
12.3 Manage Stakeholder Engagement
12.4 Monitor Stakeholder Engagement
13 Professional and Social Responsibility
13.1 Ethical Considerations in Project Management
13.2 Social Responsibility in Project Management
14 Exam Preparation
14.1 Exam Format and Structure
14.2 Study Tips and Strategies
14.3 Practice Questions and Mock Exams
14.4 Time Management During the Exam
14.5 Post-Exam Review and Feedback

5 2 Define Activities

Define Activities Explained

Define Activities Explained

Define Activities is a critical process in project management that involves identifying and documenting the specific actions required to produce the project deliverables. This process ensures that the project team understands what tasks need to be performed to achieve the project objectives. Here, we will delve into three key concepts of Define Activities: Activity List, Activity Attributes, and Milestone List.

1. Activity List

The Activity List is a comprehensive list of all the activities required to complete the project. It includes detailed descriptions of each activity, ensuring that all team members have a clear understanding of what needs to be done. The Activity List is derived from the Work Breakdown Structure (WBS) and serves as a reference for planning, scheduling, and executing the project.

Example: For a software development project, the Activity List might include tasks such as "Design User Interface," "Develop Backend Logic," "Write Unit Tests," and "Conduct User Acceptance Testing." Each task is clearly defined, ensuring that the project team knows exactly what needs to be accomplished.

2. Activity Attributes

Activity Attributes provide additional details about each activity listed in the Activity List. These attributes may include information such as activity identifiers, predecessors, successors, resource requirements, and estimated durations. Activity Attributes help in planning and managing the project by providing a comprehensive view of each activity.

Example: In a construction project, the Activity Attributes for the "Lay Foundation" task might include the activity identifier "FND-001," predecessors (e.g., "Excavate Site"), successors (e.g., "Erect Structural Frame"), required resources (e.g., concrete, labor), and estimated duration (e.g., 5 days). This detailed information helps in scheduling and resource allocation.

3. Milestone List

The Milestone List identifies key events or significant points in the project timeline. Milestones are typically high-level, time-bound events that signify the completion of major deliverables or phases. They serve as checkpoints to monitor project progress and ensure alignment with project objectives.

Example: For a marketing campaign, the Milestone List might include "Campaign Launch," "Mid-Campaign Review," and "Campaign Completion." Each milestone represents a significant achievement in the project, providing a clear indication of progress and helping to manage stakeholder expectations.