PMP
1 Introduction to Project Management
1.1 Definition of Project Management
1.2 Importance of Project Management
1.3 Project Management Framework
1.4 Project Life Cycle
1.5 Project Management Knowledge Areas
1.6 Project Management Process Groups
2 Project Environment
2.1 Organizational Structures
2.2 Organizational Process Assets
2.3 Enterprise Environmental Factors
2.4 Stakeholder Management
2.5 Project Governance
3 Project Integration Management
3.1 Develop Project Charter
3.2 Develop Project Management Plan
3.3 Direct and Manage Project Work
3.4 Monitor and Control Project Work
3.5 Perform Integrated Change Control
3.6 Close Project or Phase
4 Project Scope Management
4.1 Plan Scope Management
4.2 Collect Requirements
4.3 Define Scope
4.4 Create WBS
4.5 Validate Scope
4.6 Control Scope
5 Project Time Management
5.1 Plan Schedule Management
5.2 Define Activities
5.3 Sequence Activities
5.4 Estimate Activity Durations
5.5 Develop Schedule
5.6 Control Schedule
6 Project Cost Management
6.1 Plan Cost Management
6.2 Estimate Costs
6.3 Determine Budget
6.4 Control Costs
7 Project Quality Management
7.1 Plan Quality Management
7.2 Perform Quality Assurance
7.3 Control Quality
8 Project Resource Management
8.1 Plan Resource Management
8.2 Estimate Activity Resources
8.3 Acquire Resources
8.4 Develop Team
8.5 Manage Team
8.6 Control Resources
9 Project Communications Management
9.1 Plan Communications Management
9.2 Manage Communications
9.3 Monitor Communications
10 Project Risk Management
10.1 Plan Risk Management
10.2 Identify Risks
10.3 Perform Qualitative Risk Analysis
10.4 Perform Quantitative Risk Analysis
10.5 Plan Risk Responses
10.6 Implement Risk Responses
10.7 Monitor Risks
11 Project Procurement Management
11.1 Plan Procurement Management
11.2 Conduct Procurements
11.3 Control Procurements
12 Project Stakeholder Management
12.1 Identify Stakeholders
12.2 Plan Stakeholder Engagement
12.3 Manage Stakeholder Engagement
12.4 Monitor Stakeholder Engagement
13 Professional and Social Responsibility
13.1 Ethical Considerations in Project Management
13.2 Social Responsibility in Project Management
14 Exam Preparation
14.1 Exam Format and Structure
14.2 Study Tips and Strategies
14.3 Practice Questions and Mock Exams
14.4 Time Management During the Exam
14.5 Post-Exam Review and Feedback

5 Project Time Management

Project Time Management Explained

Project Time Management Explained

Project Time Management is a critical aspect of project management that ensures the project is completed within the defined schedule. It involves planning, estimating, scheduling, and controlling the project activities to meet the project's time objectives. Here, we will delve into five key concepts of Project Time Management: Activity Definition, Activity Sequencing, Activity Duration Estimating, Schedule Development, and Schedule Control.

1. Activity Definition

Activity Definition involves identifying and documenting the specific actions (activities) that must be performed to produce the project deliverables. This process ensures that all necessary tasks are identified and understood by the project team.

Example: For a software development project, activity definition might include tasks such as "Design User Interface," "Develop Backend Logic," and "Test Application." Each of these activities must be clearly defined to ensure the project team understands what needs to be done.

2. Activity Sequencing

Activity Sequencing involves identifying and documenting the relationships between project activities. This process helps in understanding the order in which activities must be performed to achieve the project objectives.

Example: In a construction project, activity sequencing might involve determining that "Lay Foundations" must be completed before "Erect Structures" and that "Install Utilities" must be done after "Erect Structures." This sequencing ensures that the project progresses logically and efficiently.

3. Activity Duration Estimating

Activity Duration Estimating involves estimating the number of work periods (time) needed to complete individual activities. This process helps in understanding how long each activity will take, which is crucial for developing a realistic project schedule.

Example: For a marketing campaign, activity duration estimating might involve determining that "Design Posters" will take 5 days, "Create Social Media Posts" will take 3 days, and "Execute Campaign" will take 10 days. These estimates help in planning the overall campaign timeline.

4. Schedule Development

Schedule Development involves analyzing activity sequences, activity duration estimates, and resource requirements to create the project schedule. This process ensures that the project timeline is realistic and achievable.

Example: In a software development project, schedule development might involve creating a Gantt chart that shows the start and end dates for each activity, along with dependencies and milestones. This schedule helps the project team visualize the project timeline and manage their work accordingly.

5. Schedule Control

Schedule Control involves monitoring the project schedule to ensure that the project is progressing as planned and making adjustments as necessary. This process ensures that the project stays on track and meets its time objectives.

Example: For a construction project, schedule control might involve regularly reviewing the project timeline, identifying any delays, and taking corrective actions such as reallocating resources or adjusting the schedule. This control process helps in keeping the project on schedule and mitigating any risks to the timeline.