PMP
1 Introduction to Project Management
1.1 Definition of Project Management
1.2 Importance of Project Management
1.3 Project Management Framework
1.4 Project Life Cycle
1.5 Project Management Knowledge Areas
1.6 Project Management Process Groups
2 Project Environment
2.1 Organizational Structures
2.2 Organizational Process Assets
2.3 Enterprise Environmental Factors
2.4 Stakeholder Management
2.5 Project Governance
3 Project Integration Management
3.1 Develop Project Charter
3.2 Develop Project Management Plan
3.3 Direct and Manage Project Work
3.4 Monitor and Control Project Work
3.5 Perform Integrated Change Control
3.6 Close Project or Phase
4 Project Scope Management
4.1 Plan Scope Management
4.2 Collect Requirements
4.3 Define Scope
4.4 Create WBS
4.5 Validate Scope
4.6 Control Scope
5 Project Time Management
5.1 Plan Schedule Management
5.2 Define Activities
5.3 Sequence Activities
5.4 Estimate Activity Durations
5.5 Develop Schedule
5.6 Control Schedule
6 Project Cost Management
6.1 Plan Cost Management
6.2 Estimate Costs
6.3 Determine Budget
6.4 Control Costs
7 Project Quality Management
7.1 Plan Quality Management
7.2 Perform Quality Assurance
7.3 Control Quality
8 Project Resource Management
8.1 Plan Resource Management
8.2 Estimate Activity Resources
8.3 Acquire Resources
8.4 Develop Team
8.5 Manage Team
8.6 Control Resources
9 Project Communications Management
9.1 Plan Communications Management
9.2 Manage Communications
9.3 Monitor Communications
10 Project Risk Management
10.1 Plan Risk Management
10.2 Identify Risks
10.3 Perform Qualitative Risk Analysis
10.4 Perform Quantitative Risk Analysis
10.5 Plan Risk Responses
10.6 Implement Risk Responses
10.7 Monitor Risks
11 Project Procurement Management
11.1 Plan Procurement Management
11.2 Conduct Procurements
11.3 Control Procurements
12 Project Stakeholder Management
12.1 Identify Stakeholders
12.2 Plan Stakeholder Engagement
12.3 Manage Stakeholder Engagement
12.4 Monitor Stakeholder Engagement
13 Professional and Social Responsibility
13.1 Ethical Considerations in Project Management
13.2 Social Responsibility in Project Management
14 Exam Preparation
14.1 Exam Format and Structure
14.2 Study Tips and Strategies
14.3 Practice Questions and Mock Exams
14.4 Time Management During the Exam
14.5 Post-Exam Review and Feedback

6 2 Estimate Costs

Estimate Costs Explained

Estimate Costs Explained

Estimate Costs is a critical process in project management that involves developing an approximation of the monetary resources needed to complete project activities. This process ensures that the project budget is realistic and achievable. Here, we will delve into five key concepts of Estimate Costs: Analogous Estimating, Parametric Estimating, Bottom-Up Estimating, Three-Point Estimating, and Reserve Analysis.

1. Analogous Estimating

Analogous Estimating, also known as top-down estimating, uses the cost of a previous, similar project as the basis for estimating the cost of the current project. This method is useful when there is limited information about the current project but a reliable historical data set is available.

Example: If a company has previously built a similar-sized office building for $1 million, they might use this historical data to estimate the cost of a new office building. Adjustments can be made for differences in scope, location, and other factors.

2. Parametric Estimating

Parametric Estimating uses statistical relationships between historical data and other variables to calculate an estimate. This method involves using project characteristics (parameters) to make more accurate cost predictions.

Example: In a software development project, the cost per line of code might be a parameter. If the project involves 10,000 lines of code and the cost per line is $5, the total cost estimate would be $50,000.

3. Bottom-Up Estimating

Bottom-Up Estimating involves estimating individual work items or activities and then summing them to get a total project cost. This method is more detailed and time-consuming but provides a more accurate estimate.

Example: For a construction project, the cost of materials, labor, and equipment for each activity (e.g., laying foundations, erecting structures) is estimated separately. These individual costs are then summed to get the total project cost.

4. Three-Point Estimating

Three-Point Estimating involves calculating an estimate using three different values: the most likely cost, the optimistic cost, and the pessimistic cost. This method helps in accounting for uncertainty and risk in the cost estimate.

Example: For a marketing campaign, the most likely cost is $50,000, the optimistic cost is $40,000, and the pessimistic cost is $70,000. The three-point estimate might be calculated as the average of these values, providing a more realistic cost estimate.

5. Reserve Analysis

Reserve Analysis involves adding contingency reserves or management reserves to the cost estimate to account for uncertainty and risk. Contingency reserves are added for known risks, while management reserves are added for unknown risks.

Example: In a construction project, a contingency reserve of 10% might be added to the cost estimate to account for potential delays and cost overruns. Additionally, a management reserve of 5% might be added to handle unforeseen risks.